C23-065 · Offshore Wind
Post-laytrenching&omegajointburial,USA
- Client
- Prysmian
- Tooling
- TRS1
- Region
- US East Coast
- Year
- 2023

The challenge
Trenching of two omega joints on the east and west HVAC cables, plus two 800 m sections from the offshore substation, in heavy sands with shell fragments.
Our solution
The TRS1 was deployed from a 15 Te A-frame and oriented perpendicular to focus CFE jets either side of the cable, at 2–3 m/min vessel speed.
The result
1.8 m depth of burial achieved as per contract, with no recorded delays or incidents.